Mineral
City
Sewer Extensions and Improvements
|
This project is under construction and extends sewers to problem
areas adjacent to the Village and replacement and /or rehabilitation
undersized or deteriorated existing sewers.
It also includes renovations to WWTP.
Funding is an Ohio Environmental Protection Agency revolving
loan and an
Ohio
Public Works Commission grant. Construction
began in late fall of 2007 and is scheduled to be completed on the
fall of 2008.
|
Under Construction
|
|
Stone Creek Area Sewers
|
This project is to provide a community sewer system and treatment
plant. Funding for the project is through and loan and grant from
USDA-Rural Development, an Ohio Public Works Commission loan and a
grant through the HUD GDBG Water and Sewer Program of $500,000.
The project will be advertised for construction bids in early
summer 2008, with construction anticipated to begin in the fall of
2009.
|
To bid summer 2008
|
|
Wainwright,
Port Washington
and
Ridgewood/Renner Addition SSES
|
It is important that the Sewer District reduce amount of
infiltration and inflow (I/I) entering our sewer systems during wet
weather events.
The investigation of the Ridgewood/Renner Addition sewer system
did not identify excessive infiltration, but did identify potential
sources of inflow through vented manhole covers and standard manhole
frames and covers in areas susceptible to periodic flooding.
District personnel are in the process of replacing vented
manhole covers with solid covers and installing watertight manhole
frames and covers in areas susceptible to flooding.
The District recently acquired state of technology equipment to
conduct televised inspections of problems sewers.
This equipment will enhance our investigations of the Wainwright and Port
Washington
sewer systems, as personnel and resources permit.
|
Active /Continuing Project
|
|
Wilkshire Hills Community Water Systems – Sandyville
Distribution System and Improvements of Service to Sandy
Township/Mineral City
|
The design of improvements to the Wilkshire Hills Community Water
System to the Sandy Township and Mineral City service area and to
provide water service to residents of Sandyville.
The County has received a funding offer from USDA-Rural
Development in the form of a loan and grant.
Design is expected to be complete by the end of 2008 with
construction potentially beginning in 2009.
|
Design Phase
|